Summary of the procedure Print Summary of the procedure No previous step Apply for electricity connection

Where to go?

You will have to go to the following agencies. The number indicates how many interactions are required with each entity.
Rwanda Development Board
1
Electricity, Water and Sanitation Authority (EWSA) (x 3)
2 3 4

What you will get

The objective of the procedure is to obtain those documents.
Appointment for connection works
4
Appointment for connection works 

Required documents

The documents with green band will be provided to you during the procedure.

Proof of identity
1
Proof of identity 
Application form for electricity connection
1
Application form for electricity connection 
Subscription contract form
4
Subscription contract form 
Payment receipt
4
Payment receipt 

How much?

This list shows the costs in all steps of the procedure.
Estimated cost of the procedure  RWF 56,000  
RWF 56,000 (fixed amount inclusive of quotation fees and connection works fees if the distance between the premises and the nearest electricity pole does not exceed 35 meters.) 

How long ?

The estimated total time is calculated by adding the time spent: 1) waiting in queue, 2) at the counter and 3) between steps.
  min. max.
Total time (sum): 1 d 1 d
of which:
Waiting time in queue (sum):    05mn
Attention at counter (sum):  25mn 1hr 30mn
Waiting time until next step (sum):   1 d

Legal justification?

The regulations which justify the procedure and its content