List of steps
Total number of steps : 7
|
1Submit EIA request application
Contact details
Time frame
Waiting time in queue:
max. 10mn
Attention at counter:
max. 5mn
Waiting time until next step:min. 1 d - max. 5 d Legal justificationOrganic law No. 04/2005 of 08/04/2005
(Art. 67, 69, 70) determining the modalities of protection, conservation and promotion of environment in Rwanda, Minisrerial order No 003/2008 of 15/08/2008 relating to the requirements and procedure for invironmental impact assessment. General guidelines and procedure for environment impact assesment
Additional informationThe environmental analyst will arrange an appointment with the client by phone for site visit within 5 days of receiving the application. For some projects, additional information on the project may be requested.
Recourse: Investment implementation division
|
||||||||||||||||||||||||||||||||||||||||||||||||||||